The full methodology guideline can be downloaded as separate file.
The material is primarily intended for "Digital Commissioners" of central administrative authorities and IT managers:
However, the material is recommended to be shared with other staff, broken down by position/role below:
This document has several main purposes:
This section describes the obligations and recommendations that bind to the various records associated with thread management. Most, but not all, are listed in the preceding diagram.
The descriptions are made in a numbered list that is identical to each step/stage of the cycle:
The relevance of a document to a step of the thread is marked with a cross, subsequent steps inherit this relevance:
Name of the legislation | Link (hyperlink) | 01. Need detection and initial formulation of intent (new system, major change) | 02. Qualification of the intent within the IOA/OVM (according to IK OVM) including assessment of legislative compliance | 03. Impact analysis (RIA) and legislative change^^04. Qualification of the project in the context of IKCR and OHA | 05. Allocation of financial resources for the project (budget vs ESF funds), reporting to the government^^06. Preparation of implementation (other necessary opinions, public tender) | 07. Implementation of the project (project management of implementation) | 08. Completion of implementation, evaluation (acceptance test) | 09. Operation planning including minor changes and start of operation | 10. Operation, operational supervision, implementation of minor changes and operational support^^11. Operational evaluation | 12. End of life and decommissioning | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Information Concept of the CR | https://archi.gov.cz/ikcr-dokument:ikcr | X | X | X | X | |||||||||||||||||||||||||||||
Information Concept of the Office | X |X | X |X | X |X | X |X | X |X | |||||||||||||||||||||||||||||
Methods of public administration ICT management | https://archi.gov.cz/metody-dokument:metody | x |X | X |X | X |X | X |X | X |X | X | |Decree No. 323/2002 Coll., on budgetary composition |https://www.zakonyprolidi.cz/cs/2002-323 | | | | |X | | | | | | | | | |||||||||||||||||||||
Law 110/2019 on the processing of personal data | https://www.zakonyprolidi.cz/cs/2019-110 | X | |X | X | | X |X | X |X | X |X | X | |Law 297/2016 on trust services |https://www.zakonyprolidi.cz/cs/2016-297 | |X | X | |X | X | |X | X |X | X |X | X |Act 499/2004 on archiving and filing services |https://www.zakonyprolidi.cz/cs/2004-499 | |X | X | |X | X |X | X |X | X |X | X ===== Plugging roles into individual thread steps ===== "Required" wiring is marked "P", recommended wiring is marked "D": ^ ^01. Detection of needs and initial formulation of intent (new system, major change)^02. Qualification of the intention within the IOA/OVM (according to IK OVM), including assessment of legislative compliance^^03. Impact analysis (RIA) and legislative change | 04. Qualification of the project in the context of IKCR and OHA^^05. Allocation of financial resources for the project (budget vs ESF funds), reporting to the government | 06. Preparation of implementation (other necessary opinions, public tender)^07. Implementation of the project (project management of implementation)^08. Completion of implementation, evaluation (acceptance test)^09. Operation planning including minor changes and start of operation^^10. Operation, operational supervision, implementation of minor changes and operational support | 11. Operational evaluation^12. End of life and decommissioning^ |Digital Proxy |P |P |P |P |D |P |D |P |D |P |D |P |D |P | Operations manager (technical administrator) | | | | | | | D | |P | P | P | ||||||||
Enterprise Architect, Consultant, Analyst | D | D | D | D | P |P | D | P |D |D |D |D | | D | D | |||||||||||||||||||||||||
Quality Assurance Manager (QA) | D | D | D | D | D | D | D | P | D | P | D | P | D | D | P | D | ||||||||||||||||||
Cybersecurity Manager | |D | | P | D | P | D | P | D | P | D | P | D | P | D | P | D | P | ||||||||||||||||||
Computer Specialist | D | P | D | D | D | D | D | |||||||||||||||||||||||||||
Owner of the agenda/process (substantive administrator) | P | P | P | P | P | P | D | D | ||||||||||||||||||||||||||
Supplier | |D | | D | | | P | |D |P | | D | P | |D | |
The checklist is available for download in the classic document Check list
This check-list summarises the different work packages defined in the "ICT project life cycle". Although the individual work packages are numbered and ordered to show their sequence, not every ICT Intent needs to fulfil every work package. It is only important to go through them and provide all the necessary outputs and inputs if they are relevant to the ICT plan.
Title of work package | Inputs | Outputs | Worked on as part of the intent? | ||||||
---|---|---|---|---|---|---|---|---|---|
Mandatory | Mandatory | Mandatory | Mandatory | Free text | Check-list | ||||
01. Detection of needs and initial formulation of the intention (new system, major change) | - Information concept of the CR\- Intention in the CR catalogue | - Requirements of the management of the office | - Change of the intention in the CR catalogue | Introduction into the internal database of intentions | https://spcss.archirepo.com\\\ /digitalnicesko/webapp/object/id-el-219fab6c-14be-4ab9-9873-0d4d51a7b0f6 | ☐Intent entered into the Digital Czech Republic catalogue ☐Needs mapped (requirements gathering) | |||
02. Qualification of the project within the Office of the Central Statistical Office/OVM (according to IK OVM) | - Information concept of the Office - Project in the catalogue of the Czech Republic - Evidence of the RPP - agendas, ISVS, permissions | - Change of the project in the catalogue of the Czech Republic - Necessary modifications to the RPP registration - agendas, ISVS, authorisations | ☐Change in the internal database of intentions | ||||||
03. Modification of legislation | - Analysis of the legislative environment for intentional - Impacts of changes to legislation \- RIA Methodology and Principles of Digitally Friendly Legislation | - Reason for changing or maintaining legislation \- Necessary modifications to the RPP records - agendas, ISVS, authorisations - Results of the impact analysis (RIA) - Proposal for changes to legislation | ☐RIA (form of the task catalogue of the DĆ) ☐Modified legislation\\ ☐Modifications to information in the RPP | ||||||
04. Qualification of the plan in the context of the ICCR and OHA | - Information Concept of the Czech Republic and its follow-up documents - OHA Forms | - Approved OHA form - Necessary modifications to the RPP records - agendas, ISVS, permissions] | ☐Compliance with the CR information concept\ ☐Completed OHA form\ ☐Approved OHA form\ ☐Modifications to information in the RPP\\ ☐Modifications to information in the ISVS register | ||||||
05. Allocation of financial resources for the project (budget vs. ESF funds), notification to the government | - Information to the government | - Budget systems of the office | - ESIF structures | - Acknowledgement by the government of the CR\- Change of the project in the catalogue of the Czech Republic - Calculation of the 5-year TCO (total cost of ownership) | Feasibility study | ☐Project updated in the catalogue of the Digital Czech Republic\ ☐Funding secured\ ☐Information according to ÚV86 - role in the catalogue of the Czech Republic | |||
06. Preparation of the implementation (other necessary opinions, public tender) | - Approved OHA form - Requests for comments from the subjects concerned\ - Documents for the tender procedure | - Feasibility study | - Approval of the implementation by the subjects concerned\ - Evidence in NEN - Tender documentation - Termination of tender procedure - Change of the project in the catalogue of the Czech Republic | ☐Tender published in NEN\ ☐Tender documentation created ☐Tender documentation created\ ☐Project updated in the catalogue of the Digital Czech Republic\\ ☐Implementation report 10-20% of fulfilment (task in the catalogue of the Czech Republic) | |||||
07. Implementation of the project (project management of implementation) | - Project team - ICT management methods | - Assembled team - contractor + contracting authority\ - Change of project in the catalogue of the Czech Republic | ☐Project updated in the catalogue of the Digital Czech Republic ☐Implementation report 20-90% of implementation (task in the catalogue of the Czech Republic) | ||||||
08. Completion of the implementation, evaluation (acceptance test) | - System documentation - Operating contract - Change of the project in the catalogue of the Czech Republic | ☐Implementation report = 100% (task in the catalogue of the Czech Republic) ☐Acceptance tests\ ☐Operating documentation\ ☐Operating and support agreement\ |
|||||||
09. Operation planning including minor changes and start of operation | - System documentation | - Operation contract | - Change plan | ||||||
10. Operation, operational supervision, implementation of minor changes and operational support | - System documentation - Operating agreement\ - Change plan | ||||||||
11. Operational evaluation | - System documentation - Operational contract\ - Change plan | Operational evaluation | |||||||
12. End of life and decommissioning | - Operational evaluation | - Lessons learned from implementation |